AS ON 31-03-2009
|
Programme |
No. of Schemes |
Estimated Cost Rs. in Crores |
Balance Cost in Crores |
Ayacut in Acres |
|
A) ON-GOING SCHEMES | ||||
|
88 |
604.34 |
408.96 |
145539 | |
|
67 |
429.13 |
355.72 |
81669 | |
|
2 |
36.70 |
14.78 |
9362 | |
|
9 |
2.47 |
2.01 |
1049 | |
|
SUB-TOTAL |
166 |
1072.64 |
781.47 |
237619 |
|
B) OTHER WORKS ( REVIVAL, DP LINES & IMPROVEMENTS) |
87.67 |
| ||
|
C) NEW WORKS | ||||
|
NABARD(RIDF) |
18 |
61.46 |
61.46 |
12509 |
|
86 |
843.93 |
843.93 |
112874 | |
|
SUB-TOTAL |
104 |
905.39 |
905.39 |
125383 |
|
GRAND TOTAL |
270 |
1978.03 |
1774.53 |
363002 |